San Damiano Center for Sustainability: Framing in progress, Part X

San Damiano Center for Sustainability:
Framing in Progress, Part X

by Eric Fitts, Director

Framing continued, with Eric, Bobby, Gemma, and Marty pitching in.

We installed all the underlayment on the south wall, and half on the north wall, installed all 6 windows on the north wall, and installed the exterior bathroom door. Marty stained the materials for the entry roof, we built the entry roof over the loft door, and installed underlayment on it.

Masters Week is coming! Next steps are completing the underlayment on the sheathing, installing the sliding doors, bi-fold doors, and loft door, and installing the metal roofing and metal trim and siding.

“Rebuild My Church” Capital Campaign