On the Verge of Breaking Ground!
Now that power has been switched to the new electric panel, we are ready to proceed with excavation!
Dozer at the ready
Getting this project off the ground has been a journey. Before relocating the power lines safely around the building site, the power company was delayed all fall by the power outages and then last month by rain and then snow before finally getting that done. Now, the excavator has been delayed by rain, flooding, and snow over the past three days. We are planning on excavation beginning Monday February 4th, but I am anticipating a swarm of grasshoppers will come in and gum up the backhoe ;-). Almost (but not quite) breaking ground!
All kidding aside, we are excited to get some earth moving on Monday and thankful for everyone’s partnership in the project. Stay tuned!