Worksite Updates

 

July 2020

Bonnie (3/?)

 

June 2020

Bonnie (2/?)

Caretakers Joseph and Tori, along with Summer Servant Pat, picked the project at Bonnie’s back up in June. After pulling off the first piece of metal in late May, Project Director Will realized that just putting new metal on the existing trailer roof and additions would be putting a bandaid on a much bigger issue. With 2 additions on her trailer home that had two different slopes, the path that made the most sense was a semi-roof over. We needed to make sure not to put too much weight on the existing structures so we put posts in the front but attached the roof in back through the wall which now sits on a strong foundation. Each day involved pulling tarps off the roof so we could do the work we needed and pulling them back on at the end of the day so they could keep rain out of the house. Even with the tarps, rain continued to find its way in during the rainiest part of the year. With help from the Baltimore boys, we built the shorter addition up so that we had a consistent height in the back of the house and used a transit to put a header board on posts in the front at the same height. Bonnie has been a gracious host from 10 ft away, and we love laughing with her, her daughters, granddaughter, and great granddaughters.


 

May 2020

Ann (3/3)

Caretakers and Summer Servants worked with Ann to finish up her project in the first week of June. During May they finished the front porch roof, put gutters on the whole house, built the porch in the back and added its roof, put up a fan on her front porch, and finished painting. Ann’s backyard came to life as the trees bloomed and cicadas swarmed to welcome the spring. It was hard to say a socially distant “see you later” to Ann, but we hope to see her for hugs soon. Scroll down to see the work from March-May!


 

April 2020

Ann (2/3)

In the midst of the pandemic, caretakers have retained physical distance while working to not distance socially from our local community. They returned to Ann’s house to put the metal roof and trim on, paint the house, and build her front porch and ramp. Ann was dancing on the porch before all the decking boards were even down and told us she has been eating out on her porch and enjoying the view. 


 

March 2020

Ann (1/3)

Caretakers Raine and Gemma had a demo week with groups in the second week of March. Working with Ann, they took down 2 porches and began taking the shingles off her roof. In the following weeks, a team of Caretakers went out to remove the rest of the shingles, fix rotting pieces of plywood, demolish her chimney, and get the roof under platinum paper.


 

Bonnie (1/?)

Over the first two weeks in March, Caretaker Joseph and Summer Servant Patrick McGinnis started a project with Bonnie to fix her foundation. An unsteady foundation has caused the addition on her house to pull away from the rest of the house causing leaking and roof damage. So far, they pulled off underpinning, dug holes and built piers for the new foundation, poured concrete for the base, reframed the space in between piers, and replaced the underpinning. College volunteers enjoyed hearing her hot takes on love from her decades of marriage. Still to come: fixing the damage to the roof! 


 

Leota

Caretaker Tori led groups to work with Leota over two college weeks in March. They helped repaint her house, seal her deck, replace some pieces of siding, and split and move a few truck and trailerfuls of wood. Leota told many stories, and we got many looks at the coal trains as they came rumbling down the train track next to her house. 


Caretaker Gemma brought crews to grind out a job with Paul one day and Paige the next during the first group week in March. They worked with Paul to reattach the underpinning on his house which had blown off in a storm. With Paige they sealed her roof to stop some leaks. Thanks to great weather and fast workers for helping with these jobs!


 

Jan 2020

Led by Caretakers Gemma Stanton and Joseph Reilly, groups from January jumpstarted repairs at Charlotte’s house, including a porch demo and reconstruction, fixing the back door, and improving guttering. Charlotte was an energetic cheerleader for us, helping out however she could and even providing pizza one day 🙂 Wet and slippery conditions in her yard caused a buildup of mud on the porch as we worked on it, but Joseph power washed the whole deck and steps. Now, the front porch is ready for Charlotte to relax and enjoy her stunning view of the Greenbrier River! 


 

Caretakers Steve Rassa and Tori Llorens led groups at Mike’s house in the first week of January 2020. They put a metal roof up on top of his shingles and were grateful for relatively-warm weather. A few mornings they experienced delays from snow and ice, but they finished the job in just a few weeks and Mike’s house, built by his grandmother in the ’70s, is that much safer.


 

Oct 2019

Caretaker Steve Rassa led groups at Teshla’s house through the whole summer and early fall. Bethlehem Farm executed a first site visit evaluation during the first week of July 2018 and we finally had the chance to work with her starting May 2019.

Roof – replaced rotted portions of roof and trusses, replaced soffits, installed metal roofing

Main bedroom- water damaged from leaking roof, black mold, unusable and unhealthy space. All of the unsafe and unhealthy materials were removed from the home, leaving only a shell of the room.  The room was completely renovated, installing new insulation, drywall on walls and ceiling, a new subfloor, a new laminate wood floor, and new overhead fan with lighting. 

Daughter’s bedroom:  Pulled up damaged flooring and installed new laminate Pergo flooring and molding.

Bathroom:  Home has only one bathroom.  When Teshla moved in, the shower did not function, there was no sink, and the toilet had fallen through the floor during the project but prior to renovating the bathroom (required having a portable outdoor toilet brought to her home).  The hot water heater had fallen through the rotten floor, walls, ceiling, and floor sustained major water damaged due to a leaking roof and failing plumbing.  New insulation, ceiling, walls, floor joists, subflooring, ceramic flooring, shower kit, toilet, vanity sink, and an energy efficient water heater were installed. This was the first time Teshla and her family had a functioning bathroom in over two years.


 

Sept 2019

Caretaker Joseph Reilly led groups at Missy’s house from March to September of 2019 in a project that included many different aspects. The short list?

  • Replaced 7 windows
  • Fixed the ceilings and added insulation in 4 rooms
  • Fixed the floor in 5 rooms
  • Replaced the porch roof

This project was the first to utilize our new tool trailer, and it made a world of difference to have many tools close by for whatever surprise presented itself.


 

August 2019

Caretakers Joseph and Raine and Summer Servants instructed groups to the completion of demolition and construction of a new 8’x12’ deck with 36’ of wheelchair ramp. This allowed Paul to safely make his Dr. appointments after medical complications.


 

March 2019

Steve’s first service site as a caretaker was working with Fred Elkins.  Fred has a second smaller house on his property that he uses to assist those in need.  Steve, assisted by several weeks of volunteers, removed all of the existing windows and installed 8 new replacement windows. Six of the existing windows were damaged and some with missing glass panes.  Two “windows” were mere wall openings with pinned up blankets between the freezing temperatures outdoors and the children’s bedrooms.  Eight new energy efficient windows, along with new interior and exterior moldings, were installed during the group weeks in March 2019. The home’s heating system is now able to sufficiently keep the interior space, and its occupants, warm.


 

We were excited to welcome both Greg and Josh to Community Night, as they were able to get out of their houses and come visit us because of their new wheelchair ramps this summer. We began at Greg’s by transplanting five bushes and a small tree away from the wall the ramp now runs along. For a while it looked like the bushes were goners, but they happily survived and are thriving once again. From there we dug holes and began laying lumber. The second wheelchair ramp was at Josh’s house and was a bit larger than Greg’s. However, this proved to be no match for volunteers on Adult Week and Family Week. Wielding numerous post-hole diggers (sometimes two at a time), Adult Week volunteers cleared the way for Family Week volunteers to speed through installation of deck board and railings.


 

Gloria’s home in Hinton can be seen from much of the town, as it has little additional wind blocks or neighboring buildings sheltering it from the elements. This became an issue as the exterior paint began to chip and peel. Volunteers managed to tough out sweltering June heat and now Gloria’s fresh white coat can be seen from across the river.


 

Frances lives just down the hill from Gloria. The exterior paint on the trim wood work on her home was facing similar problems and her two back buildings needed a complete new coat. Volunteers and visiting Jerusalem Farmers helped get the majority of the work done in October and November, and caretakers managed to tidy everything away before the first major snowstorm hit.